Caracas, 28 Ene. AVN.- Trabajadores de la Hidrológica de la Región Capital finalizaron en un lapso menor a 24 horas las labores de mantenimiento y recuperación programadas en los Sistemas Tuy, de acuerdo a lo reseñado por el medio Ciudad Caracas.

Hidrocapital finaliza labores de mantenimiento en los Sistemas Tuy

TL;DR

  • Maintenance and recovery work on the Tuy Systems were completed in under 24 hours.
  • The work will reintroduce 107 liters per second of water to the distribution network.
  • The goal is to stabilize the water supply for three million residents in Caracas, Miranda, and La Guaira.
  • 256 specialists performed 25 strategic actions, including replacing a 30-inch discharge valve and maintaining a 12-inch gate valve.
  • Technical corrections were made to the 85-inch main pipeline in the Camatagüita sector.
  • Electromechanical maintenance was carried out on pumping stations, and chlorine dosing and sedimentation processes were optimized at the Caujarito water treatment plant.